SAP C_TSCM42_65 Certification questions SAP Certified Application Associate – Production – Planning & Manufacturing with SAP ERP 6.0 EHP5 could be the lighthouse in your career life because it includes everything required to pass C_TSCM42_65 exam. Choosing it-exams.fr SAP C_TSCM42_65 Certification questions to help you pass the exam is a wise decision since it makes you faraway from those terrible studying days. Now, you have a helper. You can get double the result by doing half the work.

it-exams.fr SAP C_TSCM42_65 Certification questions help to ensure that you pass any SAP C_TSCM42_65 exam effortlessly. Anybody who doesn’t pass can get to come back all of buy costs in it-exams.fr C_TSCM42_65 exam. To remove the final be concerned when shopping at it-exams.fr, they have SAP C_TSCM42_65 Certification questions. Like this, you may earn good plan dependant upon your individual ruling rather then might know about claim.

QUESTION NO: 1
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)

A. Availability check
B. Digital signature
C. Resource selection
D. Electronic batch record
E. Approved master recipes

Answer: B,D,E

QUESTION NO: 2
Which of the following statements about consumption are correct? (Choose two)

A. Consumption takes place on the material level between the planned independent requirements and the planned orders.
B. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
C. Consumption is restructured with the planning run.
D. Consumption can take place between order reservations and planned independent
requirements, depending on the strategy.

Answer: B,D

QUESTION NO: 3
Where can you define the valid receivers for production order costs?

A. In the valuation variant
B. In the production scheduling profile
C. In the settlement profile
D. In the costing variant

Answer: C

QUESTION NO: 4
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?

A. Interactive single-item planning for the delayed assembly
B. Multi-level single-item planning with the “simulation mode” option
C. Total planning online
D. Multi-level single-item planning with the “display material list” option

Answer: B

QUESTION NO: 5
What does SAP ERP mean?

A. SAP ERP is a planning system in which extended planning processes can be mapped.
B. SAP ERP is a system hardware that includes modules for purchasing, sales and distribution, materials management, production and so on.
C. SAP ERP is a technological platform, on the basis of which customer-specific extensions can be imported.
D. SAP ERP is an application that an enterprise can use to manage its business processes efficiently.

Answer: D

SAP C_TSCM42_65 Certification questions

While using www.it-exams.fr SAP C_TSCM42_65 Certification questions, you not only find issues plus responses just like you may possibly properly expect via C_TSCM42_65 torrent, but you’ll go for practiced and also correct arguments so that you recruit a organization grab of the details. Simplest way to find these types of accreditations would be to log on it-exams.fr.

Collection of relevant SAP C_TSCM42_65 Certification questions according to curriculum set by the SAP Certification is not easy task to accomplish. it-exams.fr have experts who are experienced IT professionals and after years long hard work; it-exams.fr has compiled most effective SAP C_TSCM42_65 Study Materials and most advanced SAP C_TSCM42_65 Certification questions. We are confident in offering you it-exams.fr C_TSCM42_65 as an easy solution to your problems and requirements for C_TSCM42_65 exam.